The customer desired to upgrade their Maximo application and replace their legacy calibration systems to enable them to achieve a lower total cost of ownership. The customer also desired a mobile solution to manage their calibration work.
Genesis Role
Genesis provided a project manager experienced in implementing enterprise maintenance applications in the pharmaceutical industry. The project manager was responsible for planning the project timeline and resources. The project team was comprised of both customer resources and Genesis personnel.
Actions Taken
Within 15 months from the time the project plan was built, the team went live with the Maximo application for maintenance and calibration at the first site. Over 20 sites followed over the course of the next 16 months.
Results
Customer was able to save several million dollars annually due to the consolidation of systems and implementation of paperless work orders throughout their calibration and maintenance organizations
Systems & Technology Services: Major Pharmaceutical Manufacturer
The customer desired to upgrade their Maximo application and replace their legacy calibration systems to enable them to achieve a lower total cost of ownership. The customer also desired a mobile solution to manage their calibration work.
Genesis Role
Genesis provided a project manager experienced in implementing enterprise maintenance applications in the pharmaceutical industry. The project manager was responsible for planning the project timeline and resources. The project team was comprised of both customer resources and Genesis personnel.
Actions Taken
Within 15 months from the time the project plan was built, the team went live with the Maximo application for maintenance and calibration at the first site. Over 20 sites followed over the course of the next 16 months.
Results
Customer was able to save several million dollars annually due to the consolidation of systems and implementation of paperless work orders throughout their calibration and maintenance organizations